Foxwood Subdivision, London, ON

Foxwood Subdivision

London

Project scope

Project Foxwood Subdivision Phase 3 in London’s Northwest corner. There are 27 pieces of box culvert waiting to be installed along with a large box manhole to go in the middle of the sewer and over 250 meters of 1200mm Reinforced Concrete Sewer Pipe still to be laid in the ground.

Continue Reading


Oily & Storm Water Sump Pit | Sarnia, ON

Oily & Storm Water Sump Pit

Sarnia, Ontario

Project scope

Curran Contractors installed this 8-piece chamber with a seperate lid to extend over 4 middle sections of the chamber. The three-sided pieces were built with an open top and went to a chemical refinery near Sarnia.

Continue Reading


Colonel Talbot Pump Station

Colonel Talbot Pump Station

London, Ontario

Project scope

On January 21st and 22nd, Coldstream Concrete Ltd. supplied an eight-piece, custom precast concrete pump chamber to R. Russell Construction just south of Southdale Rd. in London, Ontario.

Continue Reading


Little John Road | Chatham-Kent

Little John Road

Chatham-Kent

Project scope

On November 19th Coldstream Concrete Ltd. supplied Clarke Construction with a 10-piece precast box culvert. The 3.0m x 2.7m x 20.0m long culvert was installed on Little John Road in Chatham-Kent. Total install time for the box was 6 hours.

Continue Reading


William Street | Exeter, Ontario

William St. Pump Station

Exeter

Project scope

Stone Town Construction and Coldstream Concrete Ltd. teamed up on October 15th, 2019 to install a 6.2m wide by 5.3m long superload chamber in the town of Exeter. This 9-piece custom precast structure features an internal wall and platform and can be viewed directly off of Highway #4.

Continue Reading


Sewer Upgrades & Road Widening | Fanshawe Park Road

Fanshawe Park Road

London

Project scope

In November of 2017, Land Development Solutions (LDS) presented a project that required a large 3.0m diameter maintenance hole to be put in one of the busiest commuter routes into the City of London. The project was finally awarded to CH Excavating (2013) in the Spring of 2019. In May 2019, Fanshawe Park Road West was closed in London, ON for approximately two weeks to allow for sewer upgrades, road widening and the connection of new services to a new proposed gas station just west of Hyde Park Road.

Continue Reading


Mollard Line

Mollard Line

South Huron, Ontario

Project scope

On March 7th Coldstream Concrete Ltd. supplied a fourteen-piece “ALL SKEW” precast concrete box culvert to Cope Construction in South Huron, Ontario. The culvert spans 5.6m, sits 3.35m tall and is 21.5m long. Each piece was built in our custom formwork with a 30-degree skew and weighed in at 24,255 kg. Installation took less than one day. The culvert end treatments are comprised of 128 precast concrete retaining wall blocks.

Continue Reading


Bradley Creek

Bradley Creek

Aylmer, Ontario

Project scope

On November 3, 2016, Coldstream Concrete Ltd. supplied the second half of this three-sided open-bottom culvert to the town of Aylmer, Ontario. The culvert spans 6.0 metres wide and is a low earth cover design. Due to existing hydro conduits three of the culvert pieces had to be “skated” into position after they were lowered into the excavation.

Continue Reading


Canada’s First Net-Zero, Carbon-Neutral Fire Station

Coldstream Fire Hall

Middlesex County

Project scope

Back in May 2016, Coldstream Concrete Ltd. supplied three 50,000L water reservoir tanks to Middlesex Centre’s new firehall. This hall is believed to be the first net-zero carbon neutral fire station in Canada. Once installed the tanks were connected to meet the water requirements of the new hall.

Continue Reading


New Scotland Line

New Scotland Line

Chatham-Kent, Ontario

Project scope

On December 6, 2018 Coldstream Concrete Ltd. supplied an 11-piece “ALL SKEW” precast concrete box culvert to Southshore Contracting of Essex County Inc. in Chatham Kent, Ontario. The culvert spans 2.74m, sits 2.13m tall and is 20m long. Each piece was built in our custom formwork with a 30-degree skew. Installation took one full day as mother nature was not cooperating.

Continue Reading


Edgevalley Subdivision

Edgevally Subdivision

London, Ontario

Project scope

During the 2018 summer months, Coldstream Concrete Ltd. supplied custom heavy precast and underground site servicing products to the northeast corner of London, Ontario. Phase one of this 25.4-hectare site backs onto the Thames river and will be home to over 130 detached residential lots. The SWM facility outlets into the Thames River and features a 31.5m precast concrete box culvert with a 90-degree bend, a precast three-sided, open-bottom culvert with footings, three precast headwalls and a custom precast outlet chamber…

Continue Reading


Rock Glen Road

Rock Glen Road

Municipality of Lambton Shores, Ontario

Project scope

On September 14, 2018, Coldstream Concrete Ltd. supplied a large box culvert (6m span x 2.4m rise) to the Municipality of Lambton Shores. The culvert consisted of 8 standard box units weighing 83,400 lbs each, and 1 end unit with a skew of 35o weighing 87,600 lbs. The skewed end unit was surrounded on both sides by the London Boulder Block retaining wall system (also produced by Coldstream Concrete). This system always provides an easy and decorative finish to any culvert. All 9 pieces were installed in half a day, and back-filled later the same day. The waterway was back up and running by the start of the following day.

Continue Reading


Grey Rd 10, Grey County

Grey Rd 10

Grey County, Ontario

Project scope

On June 19th 2018 Coldstream Concrete Ltd. supplied a ten-piece open-bottom precast concrete culvert to Wayne Schwartz Construction Ltd. (Miller Group) in Grey County, Ontario. The culvert spans 5.5m and sits 2.5m tall. In typical precast fashion it was installed in less than one day, resulting in shorter road closure times for the public. The second phase is set to be installed in mid August which includes a second precast culvert with similar properties of 10 + 590.

Continue Reading


Fleming Road, Plympton-Wyoming

Fleming Road

Plympton-Wyoming, Ontario

Project scope

On July 11th Coldstream Concrete Ltd. supplied a 12-piece “all skewed box culvert” for the town of Plympton-Wyoming. Each piece of he 3.6m span by 2.1m rise box culvert was constructed on a 30-degree skew. This was done in order to avoid large/heavy end units which are typical for precast skewed end culverts. Due to the fact that all pieces were designed to the same physical dimension (without large heavy end units), all 12 pieces were installed quickly and safely by 2pm the day they were delivered.

Continue Reading


Ormston Subdivision, Kitchener

Ormston Subdivision

Kitchener, Ontario

Project scope

On May 23, 2018 Coldstream Concrete Ltd. supplied a seven-piece precast concrete trench complete with approach slabs and maintenance chamber to the Ormston Subdivision in Kitchener, Ontario. The trench and all of its components were constructed using epoxy reinforcement and came equipped with concrete corbels on either side to support the precast approach slabs. Each trench piece has 6 separate galvanized steel angles cast into the concrete corners for protection and roadway grating. The trench was installed and backfilled in less than two days.

Continue Reading


Chinnick Drain and Pump Station

Chinnick Drain and Pump Station

Mun. Chatham-Kent

Project scope

In June 2015 Coldstream Concrete supplied 2 large pump stations that were 7.2m x 3.8m x 6.2m deep to the Chinnick Drain and Pump project in the Municipality of Chatham Kent. These chambers house pump intakes and collect water from the Chinnick Drain which is then pumped into Lake St. Clair. The entire one end was open to receive water from the drain. Due to the high water levels buoyancy issues had to be considered. The 3 walled chamber caused structural problems. This was remedied by inserting 25m rebar into preformed vertical tubes that extended through all the riser sections, base and cap. This created horizontal and vertical reinforcing grid and joined all the elements together. Each chamber consisted of 9 units. All 18 united were installed in the winter with water issue over 1.5 days.

Continue Reading


Bridge 417 – Thompson Line

Bridge 417 – Thompson Line

Central Elgin County

On October 15, 2015 Coldstream Concrete supplied an open bottom precast culvert that had a 11.5m span and 3.5m rise to the County of Central Elgin. Relatively dry conditions were very helpful during the installation due to the size of the watercourse and excavation. The culvert consisted of 15 units to create a 16m wide roadway. This single structure replaced a design for a dual box culvert. This is turn reduced the total project cost and created better watercourse flow. Coldstream also supplied precast concrete footings. The total installation time for footing and bridge elements was under 2 day.

Continue Reading


Open Bottom Box Culvert | Clare Ave Extension, Welland

Clare Ave Extension

Welland

Project scope

In the fall of 2015 Coldstream Concrete supplied a project to Gibbons Contracting Ltd in the City of Welland, Ontario. It consisted of a double run – open bottom box culvert with a span of 7.316m and a rise of 1.524m. The 9.0m wide road joined two subdivisions together in an area with extreme high water tables and poor soils. This all precast job consisted of 24 precast footing units, 24 precast open bottom box units and 8 different sized wing wall units. The total precast installation time in late fall was 3 days.

Continue Reading