Bradley Avenue Extension

Last year Coldstream Concrete had the honour of joining The Bradley Avenue Extension as well as The Bradley Avenue Extension & White Oak Tributary Complete Corridor projects in London, Ontario. As part of this London, Ontario road construction initiative, these projects were designed with the purpose of increasing the number of driving lanes on select roads, installing new sidewalks and landscaping, and creating a naturalized drainage channel to manage stormwater and support future development in the area.

How did Coldstream Concrete Contribute?


The Bradley Avenue Extension & White Oak Tributary Complete Corridor project in London, Ontario is a major infrastructure improvement spanning from Wharncliffe Road South to Jalna Boulevard. The project includes several complex structural elements, highlighted by a large precast open-bottom culvert system constructed in two stages. This project marks a significant milestone for Coldstream Concrete, as it represents the largest span culvert ever manufactured by the company and one of the largest precast culvert systems ever constructed in the region. The installation featured two
41.4 m runs of precast footings, and at the heart of the project, a 40.8 m long open-bottom culvert with an impressive 16.2 m span and 2.413 m rise, made up of 36 precast units weighing 42.7 tonnes each. The south half of the culvert system was successfully installed in Fall 2025, followed by the north half in Spring 2026.


What Is a Culvert, and Why Does It Matter for This Project?

A culvert is a structure that allows water to flow under a road while keeping the surface above passable. Unlike a regular culvert pipe, the culvert system used on Bradley Avenue is a large-scale open-bottom culvert, a precast design that leaves the streambed open. This makes it a preferred solution for municipal drainage culvert projects where environmental function matters as much as structural performance.

Why was Coldstream Concrete and Precast Concrete Chosen?

Coldstream Concrete's specialization in precast concrete made the company an ideal fit for this project. Because precast units are manufactured off-site at Coldstream's own facility rather than cast on location, the Bradley Avenue job site required less space for formwork and staging, and installation time was significantly reduced compared to a cast-in-place approach.


Ongoing Development


While Coldstream Concrete's involvement in the precast culvert installation phase has been completed, both the Bradley Avenue Extension and the Bradley Avenue Extension & White Oak Tributary Complete Corridor projects are set to continue development as part of London's broader infrastructure plan.



Click here for more information on The White Oaks Tributary Complete Corridor
, here for The Bradley Avenue Extension,

or here if you're interested in Coldstream Concrete’s other highlighted projects.


Contact Us Today
A construction site with a crane lifting a concrete box.
April 14, 2025
The removal and replacement of the Irwin drain culvert was successfully completed in November 2024 by Jones Group Inc. at the intersection of County Road 31 and County Road 8. Coldstream Concrete Ltd. was hired to manufacture and deliver 23.2 meters of a 5.0m x 2.8m box culvert. The precast concrete culvert was designed with custom features, including skewed ends, recessed connection plates, approach slab seats, and integrated infill sections, all cast directly into the culvert units. The entire culvert installation was efficiently completed in a single day.
Concrete pipes are stacked on top of each other in a dirt field
April 14, 2025
This vibrant community hub, spanning 57.5 hectares, includes 309 residential lots and 14 commercial/industrial blocks, providing homes for around 1,000 residents. The land was developed into eight streets, with the addition of a new pumping station and a 6-cell stormwater management pond. Featuring a wide range of Coldstream Concrete’s standard products, we successfully installed 3.5 kilometers of reinforced concrete pipe ranging from 300mm to 1800mm in diameter, multiple outlet headwalls, and over 350 round and square precast structures.
Western University Steam Tunnel Construction Site
April 14, 2025
This multi-year project, which began in 2023, is now entering its third year of construction. The project is being completed in phases with the assistance of London-based installation contractors. Every effort has been made to minimize any disruptions to students studying on campus. Phase 1 involved the installation of 64 meters of 1.5m x 0.9m steam tunnel with removable concrete lids. Phase 2 is currently in progress and, once finished, will extend the tunnel by an additional 130 meters, including the addition of a new hub to direct steam in four directions. To date, Coldstream Concrete Ltd. has produced 79 tunnel segments and 68 lids.
A black and white drawing of a prison cell with a drop of water coming out of it.

Drain Tile

A black and white circle on a white background.

Storm and Sanitary

A black and white icon of a clip in a square on a white background.

Engineered Precast